Title: Design & Construction Optimization of Diversion System of Qingxi Hydropower Station on the Furongjiang River
Abstract: Due to the restrictions of terrain,geological conditions and design schemes,the construction period of diversion engineering used to be the key control circuit in project master schedule at Qingxi Hydropower Station on the Furongjiang River in Guizhou Province.As a result of adopting author's suggestions,the design scheme and construction layout was optimized.Finally the project was not only completed ahead of the schedule,avoided the construction disturbance effectively,but also saved the project cost,and achieved good social and economic benefits.
Publication Year: 2011
Publication Date: 2011-01-01
Language: en
Type: article