Title: Management plan for the procurement of shipping casks required to service proposed federal waste repositories
Abstract: Development of transportation systems to move radioactive waste and unreprocessed spent fuel to proposed federal waste repositories is an integral part of the National Waste Terminal Storage Program. To meet this requirement, shipping casks must be designed, licensed, and fabricated. To assist the manager charged with this responsibility, a Cask Procurement Plan has been formulated. This plan is presented as a logic diagram that is suitable for computer analysis. In addition to the diagram, narrative material that describes various activities in the plan is also included. A preliminary computer analysis of the logic diagram indicates that, depending on the result of several decisions which must be made during the course of the work, the latest start dates which will allow prototype delivery of all types of casks by December 1985, range from November 1977 to March 1982.